AM - Mike Kushy and David Morrison. MK went down and the pair cleared all the materials from the bottom. Next, holes were drilled through the shuttering wood and 9 masonry holes were drilled after. 9 expansion eyebolt were inserted. These were used to hang the bang curtain with cable ties. 5 holes drilled @ 600mm, ready for charge. 3 hours. MK
PM - Mike Kushy and Jake Baynes. Holes filled and charge set off. No shrapnel and it definitely sounded quieter than previous charges. 1 hour. MK
![]() |
| Bang curtain, deployed. Photo MK. |
![]() |
| Bang curtain, tucked away. Photo MK. |